J A V A H O T E L

Project name : Java Hotel, Location : Gtl, Site area : 9000 m2, Building area : 6000 m2, Client : Java Hotel, Not Completion Yet

SKC HOTEL

Project name : SKC Hotel, Location : Gtl, Site area : 10000 m2, Building area : 6000 m2, Client : SKC, Not Completion Yet

ARH Villa

Project name : ARH Villa, Location : Denpasar - Bali, Site area : 9000 m2, Building area : 6000 m2, Client : ARH, 2007

MINIMALIS HOME

Project name : Minimalis Home, Location : Gtl, Site area : 400 m2, Building area : 120 m2, Client : Mr. IP, Completion : Under Construction

FD VILLA

Project name : FD's Villa, Location : Gtl, Site area : 300 m2, Building area : 100 m2, Client : FD's, Completion 2012

Selasa, 06 November 2012

Rumah Pribadi



Project name : Bali Modern Style | Location : Gtl | Site area : 150 m2 | Building area : 54 m2 | Client : Mr. x
Completion : under construction

Project name : Usulan Kantor SKPD  | Location : Gtl | Site area : 1000 m2 | Building area : 400 m2 | Client : ..
Completion : Not completion yet

Project name : Mushola  | Location : Gtl | Site area : 360 m2 | Building area : 90 m2 | Client : Mr. HP
Completion : under construction


Project name : Rumah Minimalis Clean  | Location : Gtl | Site area : 450 m2 | Building area : 76 m2 | Client : Mr. x
Completion : under construction



Project name : Rumah Minimalis  | Location : Gtl | Site area : 140 m2 | Building area : 108 m2 | Client : Mr. x
Completion : under construction

Project name : Rumah Minimalis  | Location : Gtl | Site area : 400 m2 | Building area : 300 m2 | Client : Mr. Iqbal Pakaya
Completion : under construction

Project name : TA's Home | Location : Gorontalo | Site area : 400 m2 | Building area : 700 m2 | Client : Mr. T Alkatiri | Completion : 2015





Project name : FD Villa | Location : Gtl | Site area : 300 m2 | Building area : 100 m2 | Client : FI | Completion : 2012 

 
Project name : AM's Home | Location : Gorontalo | Site area : 600 m2 | Building area : 450 m2 | Client : Mr. A. Monoarfa | Completion : Under construction



Project name : Kabila Town House | Location : Gorontalo | Site area : 10000 m2 | Building area : 150 m2 | Client : Mr. Gunawan | Completion : Under construction

Project name : FDs Office | Location : Gorontalo | Site area : 200 m2 | Building area : 120 m2 | Client : FI | Completion : Under construction



Project name : Masjid Agung Gorut | Location : Gtl | Site area : Building area : Client : GU Regency |  Completion : 2011



Project name : SKC Travel | Location : Gtl | Site area : Building area : 150 m2 | Client : SKC | Completion : 2011


Project name : Boarding House | Location : Gtl | Site area : 800 m2 | Building area : 2000 m2 | Client : RS | Completion : Not completion yet



Project name : Egypt House | Location : Gtl | Site area : Building area : Client : Mr. Isra Alulu | 

Completion : 2011



Project name : SJ House | Location : Gtl | Site area : | Building area : | Client : SP | Completion : Not Completion yet



Project name : Kabila Town House | Location : Kabila - Bone Bolango | Site area : 3000 m2 | Building area :      | Client : KTH Developer | Completion : under construction


Project name : RP House | Location : Gtlo | Site area :     | Building area : Client : Mr. Ramly P | Completion : 2014













Cara menghitung pondasi dangkal ( foot plate )

Untuk bisa menganalisis struktur pondasi dangkal ( foot plate ) dibutuhkan beberapa data, diantaranya :

  1. Hasil Output Analysis struktur balok, kolom, lantai, dan atap dari software konstruksi seperti ETABS, SAP2000 dll.
  2. Mutu Beton
  3. Mutu Baja
  4. Daya dukung tanah & Berat tanah
  5. Beban P Ultimate
  6. Beban M Ultimate

Garis-garis besar langkah-langkah analisis

  1. Check pondasi terhadap Tegangan Izin Tanah
  2. Hitung σmaks
  3. Hitung σmin
  4. Kontrol Tegangan Geser 1 Arah
  5. Kontrol Tegangan Geser 2 Arah (Geser Pons)
  6. Hitung Gaya Tekan Ke Atas (Geser Pons)
  7. Hitung Gaya geser yang ditahan oleh beton
  8. Hitung Hitung Penulangan Pondasi
  9. Hitung Jarak tulangan

Berikut adalah hasil analisis yang saya buat


Nah....bagi para arsitek pemula yang mungkin bingung menghitung penampang pondasi plat / telapak / poer plat
biasanya bagi anda yang ingin membuat pra-disain dengan waktu yang terbatas dan untuk keperluan perhitungan Rencana Anggaran Biaya, untuk itu anda tidak perlu mencari tenaga teknik sipil, kecuali bila pekerjaan yang anda rencanakan bukan merupakan pra-disain, berikut adalah uraian singkatnya :

Rumus :
a = Pu / ( b x l )
Pu = Beban ultimate (gaya aksial yang terjadi pada suatu kolom)
b   = Panjang pondasi telapak yang direncanakan
l    = Lebar pondasi telapak yang direncanakan
q   = Daya dukung tanah

untuk daya dukung tanah bisa dilakukan dengan cara CPT (Conus Penetration Test) / Sondir, maupun SPT (Soil Penetration Test) / Boring.
dari hasil CPT data diolah lagi dengan menggunakan rumus Meyerhof bisa juga langsung bagi FK (faktor keamanan) = 3

Data :
Pu  = 1300 kN
b    = 2 m
l     = 2 m
q    = 500 kPa

1300 / ( 2 x 2 )
325 kPa

Kontrol :
q > a
500 > 325 ----> OK


Mudah-mudahan bermanfaat
Selamat mencoba

Kamis, 01 November 2012

from 2D to 4D

dari IDE menjadi ADA

lahirnya IDE karena ADA, sesuatu yang ADA berasal dari IDE




Ini hanya memperbaiki disain yg telah dilaksanakan fisiknya oleh arsitek sebelumnya
disain lama tidak banyak memperhatikan proporsi dan irama bentuk dari bentuk bangunan utama
jadinya tercipta irama yang kacau